HMA paving on I-70 to Clear Creek

This improvement project on I-70 is 7.3 miles, starting at mile post 0 where I-70 intersects I-15 and continues to mile post 7.3. Crushing for the project began 1st of May. Some of the first steps of the project consisted of removing and reinstalling 1.1 miles of concrete barrier, milling out 2″ of existing asphalt which was then replaced with 2″ of SMA that totaled 45,000 tons and 6,000 tons of HMA.