WW Clyde is working on a data center located in Mesa, Arizona. The project involves a hefty amount of earthwork, civil work, and underground utilities.

Over 1 million tons of dirt are being moved on the project, in addition to a massive amount of underground work to install wet utilities, fiber lines, power lines, medium-voltage lines, and gas lines. Blount is also working on stormwater management throughout the area.

The logistics of a job this size are challenging. An entire support structure has been put into place to help with the project: building a mobile batch plant, offices, and infrastructure to support the construction of the building.