Harry Allen to El Dorado Transmission Line
- Owner: Desert Link, LLC (LS Power)
- Location: Las Vegas, NV
- Contract Value: $5.1M
- Completion Date: 1 Oct 2019
- Core Competencies: Earthwork
Related Projects
WW Clyde was a subcontractor to Sturgeon Electric. This project consisted of building a 59-mile long transmission line which started North of Las Vegas at the Harry Allen substation and concluded South of Henderson at the Eldorado substation. Scope included building and reclaiming approximately 83 miles of access roads, construction of 270 pads and pull sites required for construction of the towers, and pulling the wire to complete the powerline.