Mountain View Corridor construction
The cities of Eagle Mountain, Saratoga Springs, and surrounding areas are expanding every year. W.W. Clyde was contracted by UDOT on the construction of this phase of Mountain View Corridor. This section of Mountain View Corridor extends from the intersection of 2100 North and Redwood Road to S.R. 73 and will extend the already open section of MVC (2100 North from Redwood Road to I-15). Construction plans include: • Two lanes in each direction • A six-foot sidewalk on the east side • A 10-foot trail on the west side • A pedestrian and bike trail underpass at Redwood Road and 2100 North • New intersection connections at S.R. 73 and Mountain View Corridor (at Foothill Blvd) and at 2100 North and Redwood Road The major items of work for this phase of the (MVC) consists of: • Roadway Pond Excavation 355k cubic yards • Granular Borrow 64k cubic yards • UTB 50k cubic yards • HMA 62k Tons • Drainage Pipe 11.4k linear feet • Structural Concrete 584 cubic yards