This project consisted of renovating the existing football stadium. The original structure hosted its first game in 1958. Since that time, the stadium underwent numerous expansions. The University reviewed the current condition of the structure and plans for its future use and decided a complete renovation was required. AECOM worked with the University to develop a phased construction that would allow the team to continue to play football each season. Careful planning was required to accomplish this task. As the team walked off the field at the close of the 2015 season, we were on site to cover the field to allow demolition to begin. In this phased approach the process repeated itself 3 additional times. The project was intense as we completed mass excavation, rock excavation, structural excavation, soil anchors, foundation drilling, underground utilities, and asphalt paving with each phase.